Community Drainage Systems Lot-3

Community Drainage Systems Lot-3

UGX 4,627,966,029

Project Cost

6/1/2016

Start Date

Name Community Drainage Systems Lot-3
Status In Progress
Location Kawempe Division
Contractor Abubaker Technical Services & General Supplies Ltd
Supervising Consultant PROME CONSULTING ENGINEERS
Source Funding GOU (Government of Uganda)
Contract Price UGX 4627966029
Project Description [Gabunga-Kazo Angola, Nsamba-Kazo Angola, Yelemia-Kazo Angola, Lutunda, Ssekenge, Mathel, Bajabaseka Drain and Crossing]
Project Specifics a) Gabunga - Kazo Angola (440m) b) Nsamba - kazo Angola (181m) c) Yelemia - Kazo Angola (234m) e) Lutunda (560m)
Project Manager Director Engineering and Technical services
Start Date 6/1/2016 12:00:00 AM
End Date 11/20/2017 12:00:00 AM
Name Description Status Cost Assigned To Start Date
Design Update and construction Dayworks Ongoing 0 contractor 6/1/2016 12:00:00 AM
Design Update and conctruction Dayworks Ongoing 0 contractor 6/1/2016 12:00:00 AM
Design Update and construction Torrance, testing and quality control Ongoing 0 contractor 6/1/2016 12:00:00 AM
Design Update and construction Drainage structures Ongoing 0 contractor 6/1/2016 12:00:00 AM
Design Update and construction Land scaping and grassing Ongoing 0 contractor 6/1/2016 12:00:00 AM
Design Update and construction Ancillary work Ongoing 0 contractor 6/1/2016 12:00:00 AM
Design Update and construction Earth work Ongoing 0 contractor 6/1/2016 12:00:00 AM
Design Update and construction Stone-pitching and protection against erosion Ongoing 0 contractor 6/1/2016 12:00:00 AM
Design Update and construction Concrete channelling Ongoing 0 contractor 6/1/2016 12:00:00 AM
Design Update and construction Drainage including excavation,back filling, concrete works,steel works,and culvert laying Ongoing 0 contractor 6/1/2016 12:00:00 AM
Design update and construction General provision including relocation of services Ongoing 0 contractor 6/1/2016 12:00:00 AM
Design update and constrution Design update services Ongoing 0 contractor 6/1/2016 12:00:00 AM
Risk Name Category Status Probability Mitigation Contingency Assigned to Due date
Subject Details
Massive rainfall There was Slow progress of work due to frequency rainfall.
Right of way failure to obtain right of way
Massive rainfall Destruction of work due to lots of rain
Subject Details
Construction works On going a) Gabunga - concrete bed construction b) Nsamba - gabion works c) Yelemia - coping on top of stone pitched side walls d) Lutunda - concrete bed construction, stone pitching e) Ssekenge - concrete bed construction f) Bajjabaseka - concrete bed construction, stone pitching.