KIIDP2 – Design for Batch 2 drainage systems.

KIIDP2 - Design For Batch 2 Drainage Systems.

UGX 0

Project Cost

3/13/2015

Start Date

Name KIIDP2 - Design for Batch 2 drainage systems.
Status In Progress
Location Central Division,Nakawa Division,Makindye Division,Rubaga Division,Kawempe Division
Contractor KAMPALA CAPITAL CITY AUTHORITY(KCCA)
Supervising Consultant Smec International Pty Ltd
Source Funding World Bank
Contract Price UGX 0
Project Description
Project Specifics
Project Manager Director Engineering and Technical services
Start Date 3/13/2015 12:00:00 AM
End Date 12/31/2019 12:00:00 AM
Name Description Status Cost Assigned To Start Date
report for Batch 2 drainages The valuation report for Batch 2 drainages were submitted to CGV for review. A joint inspection (KCCA, RAP Consultant & CGV teams) was conducted on 29th January 2018 Complete 0 KCCA 3/1/2018 12:00:00 AM
E.O.Is for the design review and construction supervision for Lubigi The E.O.Is for the design review and construction supervision for Lubigi primary & Nakamilo Secondary drainage channels were received, evaluated. The report is being completed and is to be submitted to the Bank for clearance Ongoing 0 KCCA 3/1/2018 12:00:00 AM
Social Impact Assessment (ESIA) report Environmental and Social Impact Assessment (ESIA) report for priority drainage improvement works was received from the Bank with comments Complete 0 KIIDP Staff 3/1/2018 12:00:00 AM
Diagnostic Assesment of underground storm The evaluation of EOIs for consultancy services for Diagnostic assessment of Underground Storm Water Network in Kampala’s Central Business District and Detailed Design for rehabilitation and expansion works for Nakivubo Channel was concluded. The draft evaluation report was shared with the Bank and the team is meeting with the bank to jointly review and address comments on Monday 5th March 2018 Complete 0 KIIDP Staff 3/2/2018 12:00:00 AM
Design review of Nalukolongo Channel A kick off meeting for the design review of Nalukolongo channel and update of RAP & ESIA report was held with UB Consulting Engineers. The Contract is to run for three months Complete 0 KIIDP Staff 3/2/2018 12:00:00 AM
Submission of Batch 2 Evaluation Report The valuation report for Batch 2 drainages were submitted to CGV for review. A joint inspection (KCCA, RAP Consultant & CGV teams) was conducted on 29th January 2018. Comments from CGV are being awaited for redress. Complete 0 KIIDP Staff 3/2/2018 12:00:00 AM
Evaluatio Report submitted The valuation report for Batch 2 drainages was submitted to CGV for review. A joint inspection (KCCA, RAP Consultant & CGV teams) was conducted on 29th January 2018. The comments from the CGV are expected. Complete 0 KCCA 2/12/2018 12:00:00 AM
Risk Name Category Status Probability Mitigation Contingency Assigned to Due date
Subject Details
Right of way There is still localized right of way issues around Kyadondo junction RHS. The RAP team is working expeditiously to have these sites availed to the Contractor.
pending procurement of land Following the pending procurement of Land to relocate the Kasubi market vendors, construction works for the junction have been dropped from the current project works.
Poor drainage Poor drainage along Bakuli-Kyadondo. Rainfall runoff is stagnating on the completed base course layer. This in turn is hindering the testing of the section due to the visibly wet conditions
insufficient safety cones There are insufficient safety cones or barricades for workers in the island section of Nakulabye-Kasubi section. This practice is exposing them to the speeding motorists
Errant parking at streets of Nakulabye Kasubi There are rampant and errantly parked motor vehicles on the Bakuli-Nakulabye-Kasubi Road. These vehicles make it difficult for the contractor to execute the works especially at Nakulabye Junction.
Subject Details
E.O.Is for the design review and construction supervision The E.O.Is for the design review and construction supervision for Lubigi primary & Nakamilo Secondary drainage channels were received, evaluated. The report is being completed and is to be submitted to the Bank for clearance
(ESIA) report for priority drainage improvement works Environmental and Social Impact Assessment (ESIA) report for priority drainage improvement works was received from the Bank with comments. The comments were addressed and the report was re-submitted to the Bank on 22nd January 2018 for clearance
inception report The inception report for the design review of Nalukolongo channel and update of RAP & ESIA report from UB Consulting Engineers is under review
Lubigi channel Adjustments to the design of Lubigi channel have been concluded in-house. The in-house review of tender documents for construction of Lubigi Primary and Nakamiro Secondary Channels is being finalized as we wait for clearance of the RAP and ESIA report before tendering can begin.
Subject Details