Lot-6; Extended periodic maintenance

Lot-6; Extended Periodic Maintenance

UGX 5,583,335,380

Project Cost

6/1/2016

Start Date

Name Lot-6; Extended periodic maintenance
Status In Progress
Location Rubaga Division
Contractor Kiru General Services Ltd
Supervising Consultant Kagga and Partnerts Consulting Engineers
Source Funding URF Funding
Contract Price UGX 5583335380
Project Description RX2-0.5km in Lubaga Division, and Kayinda road-0.55km and NWSC road 0.65km in Nakawa Division
Project Specifics RX2-0.5km, Kayinda road-0.55km, NWSC road-0.65km. Total km 1.7km
Project Manager Director Engineering and Technical services
Start Date 6/1/2016 12:00:00 AM
End Date 5/26/2017 12:00:00 AM
Name Description Status Cost Assigned To Start Date
Design Update Construction including -Preliminary works, -Drainage constructions, -Pavement works including side walk ways, -Asphalt works including side walkways, -Auxillary works including road marking, road furniture and other safety measures, -Special testing and quality control, -Solar street lighting -bases Ongoing 5583335380 6/21/2016 12:00:00 AM
Risk Name Category Status Probability Mitigation Contingency Assigned to Due date
Subject Details
Right of way Failure to obtain right of way
Subject Details
Works on roads a) RX2- walkway construction, construction of gutter on RHS, drainage inlets and plastering of manholes. b) Kayinda- sub-base preparation
Subject Details
Time variation A no cost extension of the contract duration by eight (8) months bring the new contract expiry date to 19th Febraury 2018

1
Leave a Reply

avatar
Photo and Image Files
 
 
 
Audio and Video Files
 
 
 
Other File Types
 
 
 
1 Comment threads
0 Thread replies
0 Followers
 
Most reacted comment
Hottest comment thread
1 Comment authors
Owoha Recent comment authors
  Subscribe  
newest oldest most voted
Notify of
Owoha
Guest

Thank you KCCA for the good work. This project shows it is in progress but the end date was May 26th 2018. Has there been an extension of period?