Renovation of City Hall Phase II (works)

Renovation Of City Hall Phase II (works)

UGX 561,543,714

Project Cost

10/2/2013

Start Date

Name Renovation of City Hall Phase II (works)
Status Completed
Location Central Division
Contractor KAMPALA CAPITAL CITY AUTHORITY(KCCA)
Supervising Consultant KAMPALA CAPITAL CITY AUTHORITY(KCCA)
Source Funding KCCA/ NTR
Contract Price UGX 561543714
Project Description
Project Specifics Project commenced 2nd October 2013 with a duration of 6months and an extension of 82 days. Project implemented in conjunction with DAHR.
Project Manager Director Human Resource and Administration
Start Date 10/2/2013 12:00:00 AM
End Date 6/2/2014 12:00:00 AM
Name Description Status Cost Assigned To Start Date
Risk Name Category Status Probability Mitigation Contingency Assigned to Due date
Subject Details
Subject Details
Completed renovation works. Completed renovation works.